Dakota Access Pipeline Is Ordered To Shutdown Pending Environmental Impact Statement


Via Flickr

Thomas Robinson | July 7th, 2020

The Dakota Access Pipeline has been ordered to shutdown for additional environmental review after a Washington D.C. court ruling on Monday.

After more than three years post completion, a judge has ordered the Dakota Access Pipeline be emptied within 30 days to allow for further environmental review.  The judge argued that the U.S. Corps of Engineers had failed to satisfy the provisions required by the National Environmental Policy Act (NEPA) before granting an easement required for the pipeline’s construction. 

NEPA is a broad environmental law that requires environmental consideration in project planning as well as community input for federal projects.  The Trump administration has been attempting to enact changes to NEPA which would narrow the scope of the law to better assist business interests. 

The Dakota Access Pipeline crosses diagonally across Iowa and was recently approved to double the amount of oil that flows through the pipeline in Iowa.  Oil pipelines in Iowa have had issues previously, such as the spill that occurred in Worth County back in 2017. That spill is just one of 28 spills that occurred between 2000 and 2017 on pipelines owned by Magellan Midstream Partners in Iowa.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s